2017 Road Construction Projects
(page updated 6-20-17)
Below is a list of 2017 road projects to be completed within the Town of Cedarburg. They are broken up by the jurisdiction that managed the particular project.

Project Contact

2017 Town of Cedarburg Managed Projects

Adam Monticelli, Director of Public Works, (262) 377-4509. Email: Adam Project Summary: The following are the major road construction projects to be completed in 2017.

  • Pleasant Valley Road: Lofty Lane to CTH Y - Pulverize & Reshape project.
  • Douglas Lane: Western Ave south 1500’ - Pulverize & Reshape project.

Current Project Status:July 6-18 construction.


Project Contact

2017 Ozaukee County Managed Projects

Jon Edgren, Oz. Co. Highway Dept.
(262) 284-8331.
Email Jon
Project Summary: The following are the major road construction projects to be completed in 2017.

  • CTH Y: STH 60 to CTH NN – Pulverize & Repave project, August construction.
  • CTH C (Pioneer Road): Pioneer Court to CTH W (Port Washington Road) (Seal Coating, Date TBD).

Current Project Status:See above.




Project Contact

2017 State of Wisconsin Managed Projects

NA Project Summary:Nothing planned.